Franco Sarto

San Francisco, CA

Team Members

Architect:

Aubert Gregor

Highlights

  • Stand-alone retail tenant improvement
  • Venetian plaster, Serpentine walls, custom casework
  • Mechanical systems upgrade
  • 1,800 square feet
  • Franco Sarto
  • Franco Sarto

“We finished three days before the tenant needed it”

—Randy McCracken, Partner + Senior Project Manager

Biggest Challenge:

Making decisions via numerous emails

Details:

Many consultants were from out of state and didn’t fully understand the local codes. This posed a unique challenge. In order to complete the job on time, we had to interpret their designs to figure out which necessary approvals were needed. We sent numerous emails and scheduled extra meetings with city officials. In the end, we finished the job three days before the tenant needed it.

Our Company

Case Studies

Stupski Foundation

Mill Valley, CA

Union Bank of San Ramon

San Ramon, CA

CV Partners

San Francisco, CA

Vitra

Santa Monica, CA

Nordstrom / Façonnable

Costa Mesa, CA

Franco Sarto

San Francisco, CA

Atlantic Records

Hollywood, CA

Arns Law Firm

San Francisco, CA

NT Audio

Hollywood, CA

4040 Civic Center

San Rafael, CA

Information Technology

Various locations

Transamerica Pyramid Lobby

San Francisco, CA

Howard Rice

San Francisco, CA

Transamerica Pyramid Center

San Francisco, CA

View All Case Studies

Client List